Livelihood Enhancement & Protection (LEP) District Pishin

BRSP with the financial support of PPAF has implemented Livelihood Enhancement & Protection Project in 5 union councils (Rodh Malazai, Dilsora, Kwuth, Ajram & Mandozai) of District Pishin.

BRSP initially entered into an agreement with PPAF in April, 2011 for the span of two years May 2011 to April 2013 which was mutually extended for one year. Hence total duration of the project was three years starting from May 2011 to April 2014.

The project aimed to:

  • To develop the capacity, opportunities, assets and productivity of community members to reduce their vulnerability to shocks, improve their livelihoods initiatives and strengthen their business operations.

Major Deliverables of the project included; Poverty Score Card (PSC) conduction, Livelihood Enhancement Plan Development (LIPs), Capacity building of the communities, Assets provisions and CIG formation.

During the reporting period of May 2014 to April 2014, achievements against the major deliverables of the project were;

  • PSC conducted for 8,750 HH (84%) against the target 10,461 HH in 5 union Councils.
  • Total 2,814 Livelihood Investment Plans including 800 for women and 53 for disables, were developed which is 109% against the target of 2,586 LIPs.
  • 4,155 beneficiaries trained on skill, Enterprise Development and other trainings which is (107%) against the target 3898 individuals.
  • Asset provided to 1,789 Ultra/vulnerable beneficiaries (100%) against the target 1789 beneficiaries.
  • Common Interest Groups (CIG) formed 105 against the target of 93 CIGs

A graduation survey was conducted by BRSP PMER section. Based on the methodology, 95% confidence level with a confidence error margin of (±5%) status acquired by online scientific calculator, wherein a figure of 316 HH certified as sample size to represent the entire population of 1789 beneficiaries.

Cumulative Progress

Cumulative Progress against the project deliverables remained as;

Deliverables

Targets

Achievements

 PSC completed

10,461

8,750

 LIP Completed

2,586

2,814

 Training provided to person

3,898

4,155

 Person provided with wage compensation

1,255

976

 Amount provided as wage compensation (Rs)

4,016,800

1,498,400

 Assets distributed to persons

1789

1789

 Disbursement (Rs)

44,725,000

44,725,000

 CIG formed

93

105

 Linkages developed

62

3